8/14/2009 9:03:29 AM
Joyce
Posts 6
Since there are only 16 CSI divisions, how do we track costs associated with change orders without setting up separate cost codes?
8/14/2009 9:20:19 AM
admin
Posts 122
I'm sure there are other solutions, but this is one that I've seen used. How about setting up a cost code with the same number as the one with the change order, and *suffixing* "CO" on the end of the cost code. For example, say you have a cost code 0310301 that has a change order associated with it. You could set up a new cost code 0310301CO that you could code all costs for the change order.